A remote mine, a long supply chain, and a mine long reliant on diesel power and acutely sensitive to electricity costs.

The project is located in the Lubudi area of the Democratic Republic of the Congo, at site coordinates 10°35′16.3″S, 25°58′53.2″E — a low-latitude plateau in the Southern Hemisphere. It is a captive solar power plant for a mine: the electricity generated mainly replaces the mine’s purchased power, at a settlement tariff of about CNY 1.8/kWh. Grid coverage at the mine is limited, and production power has long relied on diesel generators. Fuel has to be trucked in over long distances, keeping generation costs high — the direct reason the mine decided to go solar.

Aerial view of the Lubudi project site in DR Congo: a flat, open 35MW PV array

01 Challenge 1: The sun shifts north and south each year — a fixed tilt can’t keep up

The site sits at roughly 10.6°S, where the subsolar point migrates between the Tropics over the year. Around June, the noon sun is to the north of the site; around December, it moves to the south. If the modules keep the same orientation and tilt all year, it is hard to serve both seasons well.

 

The project uses MOKUN’s manual adjustable mounting system. The modules are adjusted to face north or south, changing both orientation and tilt with the season so the array keeps a more suitable angle to the sun throughout the year. Compared with a fixed-tilt scheme, this approach trades a modest increase in mounting investment for significantly more generation.

The mine’s load is relatively stable, so PV power generated during the day can be consumed on site. The higher the cost of diesel generation, the more each extra kilowatt-hour of solar saves in fuel and generation expense. For this reason, mine projects value generation per installed kW more than typical low-tariff projects.

02 Challenge 2: Why go solar at a mine? Diesel generation is simply too expensive

Lubudi lies in the southern mining region of DR Congo, where the local grid is weak and mine production power has long relied on diesel generators. Diesel must be trucked in over long distances, and both fuel-price volatility and transport cost are built into the cost of generation, keeping the levelized cost of electricity high.

The mine’s load curve is steady and its demand is large, so solar power can be self-consumed right where it is generated, directly replacing part of the diesel output and lowering the overall cost of electricity. For projects like this, the electricity saved by each extra kilowatt-hour is worth more than the small upfront saving on the mounting structure.

For the same reason, when choosing a mounting solution the project focused on year-round generation and low maintenance effort, rather than simply comparing who offered the lowest initial price.

03 Challenge 3: Manual adjustment — one person, no special tools

MOKUN’s season-adjustable mounting system is designed on the moment-balance principle, with a tilt range of 0°–60°. One person can carry out continuous adjustment without special tools — effortless and fast.

Season-adjustable mounting system

For this project, the modules are set to face 25° north around March and 15° south around September.

Around 4–5 MWp can be adjusted per person per day, so a full seasonal switch of the 35MW site takes only a few working days.

The adjustment itself is light work — no heavy equipment or specialized crew is required. When a change is needed, staff simply come in as part of the maintenance plan, so the routine maintenance burden stays low.

Project overview

04 Incremental investment and payback

Taking the 35MW fixed-tilt scheme as the baseline, the results of the season-adjustable scheme used in this project are as follows:

Four key metrics at a glance: the adjustable system lifts annual output and revenue by about 4%, for only about 1% more initial investment

Four key metrics at a glance: the adjustable system lifts annual output and revenue by about 4%, for only about 1% more initial investment

An extra CNY 1.54 million upfront buys 1.8001 million kWh more generation and CNY 3.24 million more revenue each year. At a tariff of CNY 1.8/kWh, that incremental investment pays back in under six months.

 Cumulative cash flow after the CNY 1.54 million extra investment: positive in year 1, about CNY 79.46 million accumulated over 25 years

Looking at cumulative cash flow, incremental revenue accumulates year after year. By the end of the 25-year operating period, cumulative incremental cash flow is about CNY 79.46 million — roughly 51.6 times the incremental investment. At a tariff of CNY 1.8/kWh, the value of the generation gain is amplified even further.

05 What Kind of Projects Is This Solution Suited To?

In high-tariff captive mine power plants and low-latitude regions with pronounced north–south migration of the sun, the value of an adjustable system goes well beyond simply generating about 4% more electricity.

By latitude: where solar altitude changes markedly over the year and the sun-facing direction must switch, a single fixed tilt struggles to cover the whole year — seasonal adjustability is a sound compromise.

By tariff: in high-tariff self-consumption scenarios such as CNY 1.8/kWh, the generation gain is amplified and the payback shortens from about 1.07 years at CNY 0.8/kWh to about 0.48 years.

By adjustment: an adjustable system adds one on-site adjustment task compared with a fixed tilt, but the operation is not complicated. One person, no special tools, and a quick adjustment also let the project optimize adjustment frequency based on actual generation.

What this solution addresses is not simply laying out PV modules – it is making sure every single module faces the right sun at the right time.

Track the sun right!

Featured Resources

MOKUN Completes Shipment for 10MW Solar Project at Cement Plant in Burkina Faso

2026/09/01

MOKUN Renewable Technology Officially Selected into ACWA Power’s Class A Supplier List

2026/07/17
See All Resources

Get A Quote

For a personalized project quotation, we carefully consider your needs to create a solution that meets technical and commercial requirements.

Please enter your email below, and our representative will reach out to you as soon as possible.

bmit -->

* By submitting, I agree to be contacted by Mokun.